[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-93076":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},93076,64,1,"单选题","关于招标控制价的说法，正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","招标控制价应在招标时公布",true,{"key":16,"text":17,"correct":18},"B","招标控制价在公布后可以上调",false,{"key":20,"text":21,"correct":18},"C","招标控制价在公布后可以下浮",{"key":23,"text":24,"correct":18},"D","投标人的投标报价低于招标控制价时，投标应予以拒绝","A项，《招标投标法实施条例》规定，“招标人设有最高投标限价的，应当在招标文件中明确最高投标限价或者最高投标限价的计算方法”。BC两项，招标控制价按照计价规范的规定编制，不应上调或下浮。D项，投标报价高于招标文件设定的最高投标限价，评标委员会应当否决其投标。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]