[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-93075":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},93075,64,1,"单选题","关于工程量清单中暂列金额的说法，正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","暂列金额用于支付必然发生但暂时不能确定价格的材料等费用",false,{"key":16,"text":17,"correct":18},"B","暂列金额应列入其他项目清单",true,{"key":20,"text":21,"correct":14},"C","专业工程暂估价应列入暂列金额",{"key":23,"text":24,"correct":14},"D","承包人完成发包人提出的施工图纸以外的工作费用应列入暂列金额","AD两项，暂列金额是招标人在工程量清单中暂定并包括在合同价款中的一笔款项。它是用于施工合同签订时尚未确定或者不可预见的所需材料、设备、服务采购，施工中可能发生的工程变更、合同约定调整因素出现时的合同价款调整以及发生的索赔、现场签证确认等的费用。B项，其他项目清单包括暂列金额、暂估价、计日工和总承包服务费。C项，专业工程暂估价应列入其他项目清单中的暂估价。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]