[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-93072":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},93072,64,1,"单选题","招标人在工程量清单中提供的用于支付必然发生但暂时不能确定价格的工程设备的单价，应列入（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","暂列金额",false,{"key":16,"text":17,"correct":18},"B","工程设备暂估价",true,{"key":20,"text":21,"correct":14},"C","总承包服务费",{"key":23,"text":24,"correct":14},"D","规费","工程设备暂估价是招标人在工程量清单中提供的用于支付必然发生但暂时不能确定价格的材料、工程设备的单价及专业工程的金额，包括材料暂估单价、工程设备暂估单价、专业工程暂估价。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]