[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-93069":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},93069,64,1,"单选题","由招标人编制的分部分项工程量清单中必须包括（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","工程单价",false,{"key":16,"text":17,"correct":14},"B","工程总价",{"key":19,"text":20,"correct":21},"C","项目特征",true,{"key":23,"text":24,"correct":14},"D","项目施工方案","分部分项工程量清单应载明五个要件：①项目编码；②项目名称；③项目特征；④计量单位；⑤工程量。这五个要件在分部分项工程量清单的组成中缺一不可。分部分项工程项目清单必须根据各专业工程现行的工程量计算规范，按规定的项目编码、项目名称、项目特征、计量单位和工程量计算规则进行编制。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]