[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-93067":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},93067,64,1,"单选题","下列费用中，应包含在工程量清单项目综合单价中的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","税金",false,{"key":16,"text":17,"correct":18},"B","利润",true,{"key":20,"text":21,"correct":14},"C","贷款",{"key":23,"text":24,"correct":14},"D","规费","工程量清单计价应采用综合单价法。这里的综合单价是指完成一个规定清单项目所需的人工费、材料和工程设备费、施工机具使用费和企业管理费、利润以及一定范围内的风险费用。不论是分部分项工程项目、措施项目还是其他项目，其综合单价的组成内容均包括除规费、税金以外的所有金额。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]