[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-93059":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},93059,64,1,"单选题","某新建企业在竣工验收前，按照设计规定的工程质量标准，需对整个车间进行负荷联合试运转，发生的费用支出大于试运转收入的亏损部分应列入（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","检验试验费",false,{"key":16,"text":17,"correct":18},"B","联合试运转费",true,{"key":20,"text":21,"correct":14},"C","设备购置费",{"key":23,"text":24,"correct":14},"D","生产准备费","联合试运转费，是指新建或新增生产能力的工程项目，在交付生产前按照批准的设计文件规定的工程质量标准和技术要求，对整个生产线或装置进行负荷联合试运转所发生的费用净支出。该费用包括试运转所需材料、燃料及动力消耗、低值易耗品、其他物料消耗、机械使用费、联合试运转人员工资、施工单位参加试运转人工费、专家指导费，以及必要的工业炉烘炉费等；不包括应由安装工程费开支的单台设备调试费及无负荷联合试运转中的试车费用。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]