[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-93045":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},93045,64,1,"单选题","关于工程预付款与工程量计量的说法，正确的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","发包人按约定时间应扣回的预付款，与工程进度款同期结算抵扣",true,{"key":16,"text":17,"correct":18},"B","发包人超过约定的支付时间不支付安全文明施工费，承包人可马上停止施工",false,{"key":20,"text":21,"correct":18},"C","包工包料工程的预付款支付比例不得低于签约合同价(扣除暂列金额)的20％",{"key":23,"text":24,"correct":18},"D","对承包人超出设计图纸范围的工程量，发包人应同时予以计量","此题考查工程预付款与工程量计量相关内容。①在施工过程中，应按照合同条款中约定的时间、数额和比例，将已支付的预付款以抵充各期工程进度款的方式陆续扣回，直到扣回的金额达到合同约定的预付款金额为止。故选项A正确。②发包人没有按时支付安全文明施工费的，承包人可催告发包人支付；发包人在付款期满后的7天内仍未支付的，若发生安全事故，发包人应承担相应责任。故选项B错误。③依照《建设工程工程量清单计价规范》(GB 50500--2013)规定，包工包料工程的预付款支付比例不得低于签约合同价(扣除暂列金额)的10％，不宜高于签约合同价(扣除暂列金额)的30％。故选项C错误。④因承包人原因造成的超出合同工程范围施工或返工的工程量，发包人不予计量。故选项D错误。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]