[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-93042":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},93042,64,1,"单选题","根据《建设工程价款结算暂行办法》(2014年修订)，对于紧急抢险、救灾以及施工技术特别复杂的建筑工程，发承包双方可以采用（）方式确定合同价款：",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","工料单价",false,{"key":16,"text":17,"correct":14},"B","总价",{"key":19,"text":20,"correct":21},"C","成本加酬金",true,{"key":23,"text":24,"correct":14},"D","综合单价","根据《建设工程价款结算暂行办法》(2014年修订)中关于合同价款的约定：对于紧急抢险、救灾以及施工技术特别复杂的建筑工程，发承包双方可以采用成本加酬金方式确定合同价款。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]