[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-93040":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},93040,64,1,"单选题","根据《建设工程工程量清单计价规范》(GB50500--2013)，若因非承包人造成增加新的工程量清单项目，其工程变更价款的确定方法是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","合同中有类似的综合单价的，参照类似的综合单价确定",true,{"key":16,"text":17,"correct":18},"B","必须由承包人提出新的综合单价，经发包人确认后执行",false,{"key":20,"text":21,"correct":18},"C","必须由发包人提出并确定综合单价",{"key":23,"text":24,"correct":18},"D","必须由承包人与发包人协商确定综合单价","根据《建设工程工程量清单计价规范》(GB 50500--2013)，若因非承包人造成增加新的工程量清单项目，如果合同中已有适用的综合单价，按合同中已有的综合单价确定；如合同中有类似的综合单价，参照类似的综合单价确定：如合同中没有适用或类似的综合单价，由承包人提出综合单价，经发包人确认后执行。所以，选项A正确，而选项B、C、D中的“必须”均是不对的。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]