[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-93037":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},93037,64,1,"单选题","关于工程进度款的结算与工程量计量的说法，正确的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","发包人按约定时间应扣回的预付款，与工程进度款同期结算抵扣",true,{"key":16,"text":17,"correct":18},"B","发包人超过约定的支付时间不支付工程进度款，承包人可马上停止施工",false,{"key":20,"text":21,"correct":18},"C","应自行核实已完工程量",{"key":23,"text":24,"correct":18},"D","对承包人超出设计图纸范围的工程量，发包人应同时予以计量","对于选项B，发包人超期不支付工程进度款的，承包人可催告发包人支付，并有权获得延迟支付的利息；发包人在付款期满后的7天内仍未支付的，承包人可在付款期满后的第8天起暂停施工。而不应马上停止施工。对于选项C，承包人应按照合同约定的计量周期和时间向发包人提交当期已完工程量报告。发包人应在收到报告后7天内核实，并将核实计量结果通知发包人。而不是自行核实。对于选项D，对承包人超出设计图纸范围和因承包人原因造成返工的工程量，发包人均不予计量。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]