[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-93036":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},93036,64,1,"单选题","某土建工程2008年1_4月计划产值为1200万元，材料费占年产值60％，预付备料款占年产值25％，1-4月实际完成产值分别为200万元、300万元、400万元、300万元。当工程累计完成产值达到（）万元时，开始扣备料款。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","400",false,{"key":16,"text":17,"correct":14},"B","800",{"key":19,"text":20,"correct":14},"C","500",{"key":22,"text":23,"correct":24},"D","700",true,"预付备料款=合同总价×25％=1 200×25％：300(万元)。 起扣点=年度承包工程总值-预付备料款÷主要材料所占比重=1 200-300÷60％=700(万元)。 即：当工程累计完成产值达到700万元时，开始扣备料款。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]