[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-93034":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},93034,64,1,"单选题","下列关于工程量清单的说法中，正确的是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","其他项目费列项内容主要包括规费和税金",false,{"key":16,"text":17,"correct":14},"B","工程量清单是由投标人编制并发出的",{"key":19,"text":20,"correct":14},"C","非国有资金投资的工程建设项目不得使用工程量清单计价",{"key":22,"text":23,"correct":24},"D","全部使用国有资金投资的工程建设项目必须采用工程量清单计价",true,"本题考查有关工程量清单的相关内容。选项A的错误在于：其他项目费包括暂列金额、暂估价、计日工和总承包服务费。选项8的错误在于：工程量清单是由招标人或其委托的有资质的造价咨询机构编制的，由投标人报价。选项C的错误在于：非国有资金投资的工程建设项目宜采用工程量清单计价。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]