[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-93031":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},93031,64,1,"单选题","编制某设备安装工程概算时，发现初步设计的设备清单不完全，且设备属于价格波动较大的非标准产品。此时，较适宜采用的概算编制方法是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","预算单价法",false,{"key":16,"text":17,"correct":14},"B","扩大单价法",{"key":19,"text":20,"correct":14},"C","设备费百分比形式的概算指标法",{"key":22,"text":23,"correct":24},"D","每吨设备安装费指标形式的概算指标法",true,"在设备安装单位工程概算的编制方法中，对于概算指标法适用于两种情况：一种是按设备费的百分比计算安装工程费用，适用于价格波动不大的定型产品和通用产品；另一种是按每吨设备安装费指标计算安装工程费用，适用于设备价格波动较大的非标准设备和引进设备。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]