[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-93019":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},93019,64,1,"单选题","在工程量清单计价模式下，关于确定分部分项工程项目综合单价的说法，错误的是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","若分部分项工程量项目特征的描述与设计图纸不符，投标人应按分部分项工程量项目特征的描述确定综合单价",false,{"key":16,"text":17,"correct":14},"B","综合单价中需考虑招标文件中要求投标人承担的风险费用",{"key":19,"text":20,"correct":21},"C","综合单价中应考虑招标人和投标人共同承担的所有风险费用",true,{"key":23,"text":24,"correct":14},"D","招标文件中提供了暂估单价的材料，应按暂估单价计入综合单价","关于选项C，综合单价中应考虑招标文件中要求投标人承担的风险费用，而不是招标人和投标人共同承担的所有费用。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]