[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-93014":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},93014,64,1,"单选题","招标工程以投标截止日前（）天，非招标工程以合同签订前（）天为基准日，其后国家的法律、法规、规章和政策发生变化引起工程造价增减变化的，发承包双方应按照省级或行业建设主管部门或其授权的工程造价管理机构据此发布的规定调整合同价款。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","28，14",false,{"key":16,"text":17,"correct":14},"B","14，7",{"key":19,"text":20,"correct":21},"C","28，28",true,{"key":23,"text":24,"correct":14},"D","42，42","招标工程以投标截止日前28天，非招标工程以合同签订前28天为基准日，其后国家的法律、法规、规章和政策发生变化引起工程造价增减变化的，发承包双方应按照省级或行业建设主管部门或其授权的工程造价管理机构据此发布的规定调整合同价款。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]