[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-93012":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},93012,64,1,"单选题","下列工程施工过程发生的事件中，属于对合同款不予调整的是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","招标T程量清单项目特征描述与图纸不符引起工程量增加",false,{"key":16,"text":17,"correct":14},"B","工程量清单缺项引起工程量增加",{"key":19,"text":20,"correct":14},"C","招标人提出的工程变更引起措施项目发生变化",{"key":22,"text":23,"correct":24},"D","因承包人导致工期延误，在原定竣丁时间后税收政策调整引起合同价款增加",true,"前三个选项都应对合同款予以调整；而因承包人导致工期延误的，在合同工程原定竣工时间之后，合同价款调增的不予调增，合同价款调减的予以调整。故选项D属于对合同款不予调整的事件。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]