[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-93011":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},93011,64,1,"单选题","根据《建设工程工程量清单计价规范》(GB50500--2013)，关于确定因非承包人引起工程量增减的综合单价的说法，正确的是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","因合同中已有适用的综合单价，故应继续按合同中已有的综合单价执行",false,{"key":16,"text":17,"correct":14},"B","必须由承包人提出新的综合单价．经发包人确认后执行",{"key":19,"text":20,"correct":21},"C","若该工程量的变化在合同约定幅度以内．应执行原有的综合单价",true,{"key":23,"text":24,"correct":14},"D","若该项工程量变化在合同约定幅度以外．其综合单价应予以调整．但措施费不能调整","根据《建设工程工程量清单计价规范》(GB 50500--2013)，关于确定因非承包人引起工程量增减，如果工程量变化在合同约定幅度以内的，应执行原有的综合单价，故选项C正确；但如果工程量变化在合同约定幅度以外，其综合单价及措施费均应予以调整．故选项D不正确。选项A、B均太绝对了，不正确。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]