[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-93009":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},93009,64,1,"单选题","建设工程的可调值总价合同与不可调值总价合同的区别在于，发包方承担了（） 的风险。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","通货膨胀",true,{"key":16,"text":17,"correct":18},"B","生产条件恶劣",false,{"key":20,"text":21,"correct":18},"C","气候条件恶化",{"key":23,"text":24,"correct":18},"D","其他意外","建设工程的可调值总价合同与不可调值总价合同的区别在于，发包方承担了通货膨胀这一可预测费用因素的风险。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]