[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-93004":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},93004,64,1,"单选题","用资金周转率法估算某项目建设投资，已知该项目资金周转率的近似值为1．5，项目生产期产品的年产量为600万吨，产品价格为80元\u002F吨，该项目总投资估计应为（）万元。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","32000",true,{"key":16,"text":17,"correct":18},"B","36000",false,{"key":20,"text":21,"correct":18},"C","45000",{"key":23,"text":24,"correct":18},"D","72000","本题考查的是资金周转率法估算建设投资。总投资额=产品的年产量×产品单价÷资金周转率=600×80÷1．5=32000(万元)。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]