[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-93001":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},93001,64,1,"单选题","根据《建设工程工程量清单计价规范》，关于建设工程工程量清单计价的说法，错误的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","全部使用国有资金投资或国有资金投资为主的建设工程施工发承包，必须采用工程量清单计价",false,{"key":16,"text":17,"correct":18},"B","非国有资金投资的工程建设项目，不应采用工程量清单方式计价",true,{"key":20,"text":21,"correct":14},"C","分部分项工程量清单采用综合单价方式计价",{"key":23,"text":24,"correct":14},"D","实行工程量清单招标时，工程量清单应由具有编制能力的招标人或受其委托的具有相应资质的工程造价咨询人编制。","关于工程量清单招标的相关内容中，选项B错误；非国有资金投资的工程建设项目，不是“不应采用”而是“宜采用”工程量清单方式招标。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]