[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-92995":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},92995,64,1,"单选题","相对于工程实体而言，对实际施工中必须发生的施工准备和施工过程中技术、生活、安全、环境保护等方面的非工程实体项目的总称是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","其他项目",false,{"key":16,"text":17,"correct":14},"B","分部分项工程项目",{"key":19,"text":20,"correct":14},"C","规费项目",{"key":22,"text":23,"correct":24},"D","措施项目",true,"“措施项目”相对于工程实体的分部分项工程项目而言，是对实际施工中必须发生的施工准备和施工过程中技术、生活、安全、环境保护等方面的非]：程实体项目的总称。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]