[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-92980":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},92980,64,1,"单选题","根据《建设工程工程量清单计价规范》(GB 50500--2013)，下列关于分部分项工程量清单的说法正确的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","分部分项工程量清单的项目编码应采用9位阿拉伯数字表示",false,{"key":16,"text":17,"correct":18},"B","同一招标工程的项目编码不得有重复",true,{"key":20,"text":21,"correct":14},"C","分部分项工程量清单的项目名称可由编制者根据需要自行拟定",{"key":23,"text":24,"correct":14},"D","分部分项工程量清单中所列工程量的有效位数均应保留小数点两位","选项A错误，分部分项工程量清单的项目编码应采用12位阿拉伯数字表示；选项C错误，分部分项工程量清单的项目名称应按《建设工程工程量清单计价规范》(GB 50500—2013)附录的项目名称结合拟建工程的实际确定：选项D错误，工程量的有效位数不一定是保留两位小数。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]