[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-92958":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},92958,64,1,"单选题","《建设工程工程量清单计价规范》规定，分部分项工程量清单的项目编码，应采用12位阿拉伯数字表示，其中第1、2位为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","附录分类顺序码",false,{"key":16,"text":17,"correct":18},"B","专业工程代码",true,{"key":20,"text":21,"correct":14},"C","清单项目名称顺序码",{"key":23,"text":24,"correct":14},"D","分项工程名称顺序码","本题考查《建设工程工程量清单计价规范》。《建设工程工程量清单计价规范》规定，分部分项工程量清单的项目编码，应采用12位阿拉伯数字表示，其中第1、2位为专业工程代码；第3、4位为附录分类顺序码；第5、6位为分部工程顺序码；第7-9位为分项工程名称顺序码；第10-12位为清单项目名称顺序码。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]