[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-92952":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},92952,64,1,"单选题","在竣工验收阶段，建设单位要对从筹建到竣工投产全过程的全部实际支出的费用进行汇总，编制（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","竣工结算",false,{"key":16,"text":17,"correct":14},"B","施工结算",{"key":19,"text":20,"correct":21},"C","竣工决算",true,{"key":23,"text":24,"correct":14},"D","施工图预算","本题考查的竣工决算的含义。四个选项中，只有竣工决算是由建设单位要编制的，其他三个选项均由施工单位编制。竣工决算是建设单位从筹建到竣工投产全过程的全部实际支出的总费用。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]