[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-92945":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},92945,64,1,"单选题","因承包人原因造成的超出合同工程范围施工或返工的工程量，发包人( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","不予计量",true,{"key":16,"text":17,"correct":18},"B","应予计量",false,{"key":20,"text":21,"correct":18},"C","应酌情计量",{"key":23,"text":24,"correct":18},"D","应予处罚","此题考查期中结算的工程计量相关内容。在工程计量中，工程量必须按照相关工程现行国家计量规范规定的工程量计算规则计算。工程计量可选择按月或按工程形象进度分段计量，具体计量周期应在合同中约定。因承包人原因造成的超出合同工程范围施工或返工的工程量，发包人不予计量。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]