[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-92943":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},92943,64,1,"单选题","当合同中没有约定价格变化的范围或幅度，材料、工程设备单价变化超过( )时，超过部分的价格应按照价格指数调整法或造价信息差额调整法计算调整相关费用。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","1％",false,{"key":16,"text":17,"correct":14},"B","3％",{"key":19,"text":20,"correct":21},"C","5％",true,{"key":23,"text":24,"correct":14},"D","10％","此题考查物价变化引起合同价款调整原则。合同履行期间，因人工、材料、工程设备、机械台班价格波动影响合同价款时，应根据合同约定调整合同价款。承包人采购材料和工程设备的，应在合同中约定主要材料、工程设备价格变化的范围或幅度；当没有约定，且材料、工程设备单价变化超过5％时，超过部分的价格应按照价格指数调整法或造价信息差额调整法计算调整材料、工程设备费用。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]