[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-92942":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},92942,64,1,"单选题","根据《建设工程工程量清单计价规范》(GB50500---2013)规定，招标工程以投标截止日前( )天，非招标工程以合同签订前( )天为调整合同价款基准日。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","7；14",false,{"key":16,"text":17,"correct":14},"B","14；14",{"key":19,"text":20,"correct":14},"C","14；28",{"key":22,"text":23,"correct":24},"D","28；28",true,"此题考查法律法规变化引起合同价款调整的内容。招标工程以投标截止日前28天，非招标工程以合同签订前28天为基准日，其后国家的法律法规、规章和政策发生变化引起工程造价增减变化的，发承包双方应当按照有关规定调整合同价款。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]