[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-92941":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},92941,64,1,"单选题","采用总费用法计算索赔，适用于( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","采取低价策略中标的工程",false,{"key":16,"text":17,"correct":14},"B","总索赔费用较大的工程",{"key":19,"text":20,"correct":21},"C","多个索赔事件混杂在一起的工程",true,{"key":23,"text":24,"correct":14},"D","采用固定总价合同的工程","此题考查索赔费用计算。索赔费用的计算方法分为分项法和总费用法两种。总费用法是指当发生多次索赔事件后，重新计算出该工程的实际总费用，再从这个实际总费用中减去投标报价总费用，计算出索赔金额。采用这种方法计算索赔额，往往包含许多不合理因素。因此，只有当多个索赔事件混杂在一起，难以准确地进行分项记录和资料收集，不易计算出具体费用损失时，才会采用总费用法计算索赔额。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]