[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-92940":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},92940,64,1,"单选题","在竣工结算时，暂列金额应减去工程价款调整与索赔、现场签证金额计算，如有余额归( )所有。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","承包人",false,{"key":16,"text":17,"correct":18},"B","发包人",true,{"key":20,"text":21,"correct":14},"C","发包人和承包人共同",{"key":23,"text":24,"correct":14},"D","监理人","此题考查暂列金额部分竣工结算。暂列金额应减去合同价款调整(包括索赔、现场签证)金额计算，若有余额，则余额归发包人；若出现差额，则由发包人补足并反映在相应的工程合同价款中。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]