[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-92939":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},92939,64,1,"单选题","施工中进行工程计量，因工程变更引起工程量增减时，应按( )计算。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","由造价咨询人重新进行编制的工程量清单",false,{"key":16,"text":17,"correct":18},"B","承包人在履行合同义务中完成的工程量",true,{"key":20,"text":21,"correct":14},"C","承包人计量报告中所列的工程量",{"key":23,"text":24,"correct":14},"D","双方协商的工程量","此题考查期中价款结算工程计量内容。由于招标工程量清单所列的工程量是一个预计工程量，发承包双方结算的工程量应以承包人按照现行国家计量规范计算的实际完成应予计量的工程量确定。施工中进行工程计量，当发现招标工程量清单中出现缺项、工程量偏差，或因工程变更引起工程量增减时，应按承包人在履行合同义务中完成的工程量计算。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]