[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-92936":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},92936,64,1,"单选题","以下关于提前竣工说法正确的是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","是否提前竣工由承包人决定",false,{"key":16,"text":17,"correct":18},"B","提前竣工由发包人提出，并经承包人同意",true,{"key":20,"text":21,"correct":14},"C","提前竣工导致的增加费用应列入合同文件中",{"key":23,"text":24,"correct":14},"D","压缩工期不得超过额定工期的10％","此题考查提前竣工相关内容。招标人应依据相关工程的工期定额合理计算工期，压缩工期的天数不得超过定额工期的20％，超过者应在招标文件中明示增加赶工费用。发包人要求合同工程提前竣工的，应征得承包人同意后与承包人商定采取加快工程进度的措施，并应修订合同工程进度计划；发包人应承担承包人由此增加的提前竣工(赶工补偿)费用。发承包双方应在合同中约定提前竣工每日历天应补偿的额度，此项费用应作为增加合同价款项列入竣工结算文件中，与结算款一并支付。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]