[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-92928":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},92928,64,1,"单选题","关于工程量清单的说法，正确的是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工程量清单计价应采用工料单价法",false,{"key":16,"text":17,"correct":18},"B","招标工程量清单是工程量清单计价的基础",true,{"key":20,"text":21,"correct":14},"C","招标工程量清单由分部分项工程项目清单、措施项目清单、其他项目清单组成",{"key":23,"text":24,"correct":14},"D","招标工程量清单应以整个建设项目为单位编制","此题考查对工程量清单的理解。工程量清单是载明建设工程分部分项工程项目、措施项目和其他项目的名称和相应数量等内容的明细清单。在不同阶段，又可分别称为招标工程量清单和已标价工程量清单等。招标工程量清单是工程量清单计价的基础，应作为编制招标控制价、投标报价、计算或调整工程量、施工索赔等的重要依据。工程量清单计价应采用综合单价法。招标工程量清单应以单位(项)工程为单位编制，由分部分项工程项目清单、措施项目清单、其他项目清单、规费和税金项目清单组成。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]