[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-92921":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},92921,64,1,"单选题","在工程施工过程中，由于发包方提出工程变更，导致该清单项目的工程数量发生变化超过( )时，应调整项目单价。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","10％",false,{"key":16,"text":17,"correct":14},"B","12％",{"key":19,"text":20,"correct":21},"C","15％",true,{"key":23,"text":24,"correct":14},"D","21％","此题考查工程变更引起分部分项工程费的调整。已标价工程量清单中有适用于变更工程项目的，采用该项目的单价。但当工程变更导致该清单项目的工程数量发生变化超过15％时，应调整项目单价。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]