[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-92920":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},92920,64,1,"单选题","根据《建设工程工程量清单计价规范》，关于工程量偏差引起合同价格调整的说法，正确的是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","当工程量增加15％以上时，其增加部分的工程量综合单价应予调低",true,{"key":16,"text":17,"correct":18},"B","当工程量增加15％以上时，全部的工程量综合单价应予调低",false,{"key":20,"text":21,"correct":18},"C","当工程量减少15％以上时，减少后剩余部分的工程量综合单价应予调低",{"key":23,"text":24,"correct":18},"D","当工程量减少15％以上时，全部的工程量综合单价应予调低","此题考查工程量偏差引起的合同价款调整。合同履行期间如出现工程量偏差，发承包双方应调整合同价款。当工程量增加15％以上时，其增加部分的工程量综合单价应予调低；当工程量减少15％以上时，减少后剩余部分的工程量综合单价应予调高。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]