[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-92919":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},92919,64,1,"单选题","根据《建设工程工程量清单计价规范》(GB50500--2013)规定，采用( )时，承包人不承担任何价格变化的风险。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","成本加酬金合同",true,{"key":16,"text":17,"correct":18},"B","固定单价合同",false,{"key":20,"text":21,"correct":18},"C","变动总价合同",{"key":23,"text":24,"correct":18},"D","固定总价合同","此题考查对成本加酬金合同的理解。《建设工程工程量清单计价规范》(GB 50500—2013)规定，成本加酬金合同是指发承包双方约定以施工工程成本再加合同约定酬金进行合同价款计算、调整和确认的建设工程施工合同。采用成本加酬金合同，承包人不承担任何价格变化的风险。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]