[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-92918":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},92918,64,1,"单选题","关于建设工程承包合同价格的说法，正确的是( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","工程量清单项目综合单价任何情况下都是不允许调整的",false,{"key":16,"text":17,"correct":14},"B","成本加酬金合同使承包方承受较大风险",{"key":19,"text":20,"correct":14},"C","紧急抢险的建设工程，可以采用总价合同",{"key":22,"text":23,"correct":24},"D","依据《建设工程工程量清单计价规范》，实行工程量清单计价的工程，宜采用单价合同",true,"此题考查承包合同价款。实行工程量清单计价的工程，应当采用单价合同。单价合同约定的工程价款中所包括的工程量清单项目综合单价，在约定条件内是固定的、不予调整，而工程量允许调整；工程量清单项目综合单价在约定条件外的，允许调整，但调整方式和方法应在合同中约定。紧急抢险、救灾以及施工技术特别复杂的建设工程，可以采用成本加酬金合同。采用成本加酬金合同，承包人不承担任何价格变化的风险。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]