[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-92917":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},92917,64,1,"单选题","施工过程中，当出现的风险内容及其范围在招标文件规定的范围内时，则( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","综合单价可以变动",false,{"key":16,"text":17,"correct":14},"B","综合单价可以变动，工程款可以调整",{"key":19,"text":20,"correct":21},"C","综合单价不得变动",true,{"key":23,"text":24,"correct":14},"D","综合单价不得变动，但工程款可以调整","此题考查投标报价时综合单价的确定。投标报价的综合单价应包括招标文件中划分的应由投标人承担的风险范围及其费用。招标文件中没有明确的，应提请招标人明确。在施工过程中，当风险内容及其范围(幅度)在招标文件规定的范围(幅度)内时，综合单价不得改变，合同价款不作调整。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]