[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-92914":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},92914,64,1,"单选题","施工降水工程应属于( )中的内容。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","分部分项工程量清单",false,{"key":16,"text":17,"correct":18},"B","措施项目清单",true,{"key":20,"text":21,"correct":14},"C","其他项目清单",{"key":23,"text":24,"correct":14},"D","规费项目清单","此题考查工程量清单相关内容。招标工程量清单应以单位(项)工程为单位编制，由分部分项工程项目清单、措施项目清单、其他项目清单、规费和税金项目清单组成。其中，措施项目可划分为两类：一类是“总价项目”，如文明施工和安全防护、临时设施等，此类项目在现行国家计量规范中无工程量计算规则，应以总价(或计算基础乘费率)计算，以“项”计价；另一类是“单价项目”，如脚手架、施工降水工程等，可根据工程图纸(含设计变更)和国家现行相关工程计量规范规定的工程量计算规则进行计量，以“量”计价。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]