[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-92913":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},92913,64,1,"单选题","紧急抢险、救灾以及施工技术特别复杂的建设工程，可以采用( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","单价合同",false,{"key":16,"text":17,"correct":14},"B","总价合同",{"key":19,"text":20,"correct":21},"C","成本加酬金合同",true,{"key":23,"text":24,"correct":14},"D","以上均可","此题考查承包合同计价方式选择。紧急抢险、救灾以及施工技术特别复杂的建设工程，可以采用成本加酬金合同。成本加酬金合同是指发承包双方约定以施工工程成本再加合同约定酬金进行合同价款计算、调整和确认的建设工程施工合同。采用成本加酬金合同，承包人不承担任何价格变化的风险。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]