[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-92907":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},92907,64,1,"单选题","当初步设计的设备清单不完备，或仅有成套设备的重量时，可采用( )编制设备安装工程费用概算。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","预算单价法",false,{"key":16,"text":17,"correct":18},"B","扩大单价法",true,{"key":20,"text":21,"correct":14},"C","概算指标法",{"key":23,"text":24,"correct":14},"D","概算定额法","此题考查单位设备安装工程费用概算编制方法选取。设备安装工程费用概算编制方法有预算单价法、扩大单价法和概算指标法等。当初步设计的设备清单不完备，或仅有成套设备的重量时，可采用主体设备、成套设备或生产工艺线的综合扩大安装单价编制概算。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]