[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-92903":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},92903,64,1,"单选题","对于大型建设项目而言，项目总投资中流动资金的估算宜采用( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","分项详细估算法",true,{"key":16,"text":17,"correct":18},"B","设备费用百分比法",false,{"key":20,"text":21,"correct":18},"C","生产能力指数法",{"key":23,"text":24,"correct":18},"D","资金周转率法","此题考查流动资金估算方法。项目总投资中的流动资金是指在生产性项目建成投产后，为进行正常生产运营，用于购买原材料、燃料，支付工资及其他经营费用等所需的周转资金。流动资金估算一般采用分项详细估算法，个别情况或者小型项目可采用扩大指标法。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]