[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-92902":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},92902,64,1,"单选题","关于项目总投资中流动资金的说法，正确的是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","流动资金估算一般采用分项详细估算法",true,{"key":16,"text":17,"correct":18},"B","采用扩大指标估算法估算流动资金，方法简便易行，准确度较高",false,{"key":20,"text":21,"correct":18},"C","项目总投资中的流动资金是指项目建设期内占用的资金",{"key":23,"text":24,"correct":18},"D","流动资金应列入建设工程造价","此题考查流动资金相关内容。项目总投资中的流动资金是指在生产性项目建成投产后，为进行正常生产运营，用于购买原材料、燃料，支付工资及其他经营费用等所需的周转资金。流动资金估算一般采用分项详细估算法，个别情况或者小型项目可采用扩大指标法。扩大指标估算法简便易行，但准确度不高。生产性建设项目的总投资包括建设投资、建设期利息和流动资金三部分，而建设工程造价就是建设投资和建设期利息之和。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]