[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-92880":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},92880,64,1,"单选题","根据建设工程造价构成，场地准备费和临时设施费属于( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工程费用",false,{"key":16,"text":17,"correct":18},"B","工程建设其他费用",true,{"key":20,"text":21,"correct":14},"C","预备费",{"key":23,"text":24,"correct":14},"D","建设期利息","此题考查工程建设其他费用相关内容。工程建设其他费用可分为三类，即土地使用费和其他补偿费、与工程建设过程有关的费用、与工程未来生产经营有关的费用。其中，与工程建设过程有关的费用包括建设管理费、可行性研究费、专项评价费、研究试验费、勘察设计费、场地准备费和临时设施费、引进技术和进口设备材料其他费、特殊设备安全监督检验费、市政公用配套设施费、工程保险费、专利及专有技术使用费",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]