[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-92859":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},92859,64,1,"单选题","在时标网络计划中，通过绘制某检查时刻工程实际进度前锋线，进行工程实际进度与计划进度比较的方法是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","横道图比较法",false,{"key":16,"text":17,"correct":18},"B","前锋线比较法",true,{"key":20,"text":21,"correct":14},"C","列表比较法",{"key":23,"text":24,"correct":14},"D","香蕉曲线比较法","在工程网络计划执行过程中，当收集到实际进展数据需要与计划进度数据进行比较分析时，常用的比较方法有前锋线比较法和列表比较法。其中，前锋线比较法是指在时标网络计划中通过绘制某检查时刻工程实际进度前锋线，进行工程实际进度与计划进度比较的方法。列表比较法是记录检查日期应进行的工作名称及已作业时间，然后列表计算有关时间参数，并根据工作总时差进行实际进度和计划进度比较的方法。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]