[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-92849":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},92849,64,1,"单选题","在某单代号网络计划中，工作C有 D、 E、G三项紧后工作，其总时差分别为3天、5天、6天，工作C与紧后工作 D、 E、G之间的时间间隔分别为7天、2天、3天，则工作C的总时差是（ ）天。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","3",false,{"key":16,"text":17,"correct":14},"B","5",{"key":19,"text":20,"correct":14},"C","6",{"key":22,"text":23,"correct":24},"D","7",true,"在单代号网络计划中，网络计划终点节点n所代表的工作的总时差应等于计划工期与计算工期之差，非网络计划终点节点工作的总时差应等于本工作与其各紧后工作之间的时间间隔加该紧后工作的总时差所得之和的最小值。本题中，工作C的总时差TF＝min（3＋7，5＋2，6＋3）＝min（10，7，9）＝7（天）。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]