[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-92843":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},92843,64,1,"单选题","某单代号网络计划中，工作M有三项紧后工作，工作M与各项紧后工作之间的时间间隔分别为3天、5天和6天，则工作M的自由时差是（ ）天。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","3",true,{"key":16,"text":17,"correct":18},"B","5",false,{"key":20,"text":21,"correct":18},"C","6",{"key":23,"text":24,"correct":18},"D","14","在单代号网络计划中，除以终点节点为完成节点的工作外，其他工作的自由时差等于本工作与其紧后工作之间时间间隔的最小值。故工作M的自由时差＝min（3，5，6）＝3（天）。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]