[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-92838":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},92838,64,1,"单选题","某工程双代号网络计划中，工作M的最早开始时间是第8天，其持续时间为5天。该工作有三项紧后工作，其最迟开始时间分别为第16天、第18天、第19天。则工作M的总时差是（ ）天。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","3",true,{"key":16,"text":17,"correct":18},"B","5",false,{"key":20,"text":21,"correct":18},"C","6",{"key":23,"text":24,"correct":18},"D","8","本题中，工作M的最早完成时间＝工作M的最早开始时间＋工作M持续时间＝8＋5＝13（天）；工作M的最迟完成时间应等于其所有紧后工作最迟开始时间的最小值，故工作M的最迟完成时间为16天；工作M的总时差等于该工作最迟完成时间与最早完成时间之差，即16－13＝3（天）。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]