[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-92829":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},92829,64,1,"单选题","关于网络计划中虚箭线的说法，正确的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","虚箭线是一项工作，不占用时间，只消耗资源",false,{"key":16,"text":17,"correct":14},"B","虚箭线是一项虚拟工作，不消耗资源，只占用时间",{"key":19,"text":20,"correct":21},"C","虚箭线是一项虚拟工作，不占用时间，也不消耗资源",true,{"key":23,"text":24,"correct":14},"D","虚箭线是一项工作，既占用时间，又消耗资源","双代号网络计划又称箭线式网络计划，它是以箭线及其两端节点编号表示工作的进度计划。同时，节点又表示工作的开始或结束以及工作之间的连接状态。双代号网络计划中，有时存在虚箭线（称为虚工作），虚工作既不消耗时间，也不消耗资源，主要用来表示相邻两项工作之间的逻辑关系。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]