[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-92827":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},92827,64,1,"单选题","某工程双代号网络计划中，工作Z的持续时间为6天，最早完成时间是第12天，工作Z的总时差为7天，则工作Z的最迟开始时间是第（ ）天。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","7",false,{"key":16,"text":17,"correct":14},"B","10",{"key":19,"text":20,"correct":21},"C","13",true,{"key":23,"text":24,"correct":14},"D","18","工作的总时差等于该工作最迟完成时间与最早完成时间之差，或该工作最迟开始时间与最早开始时间之差。本题中，工作Z的总时差＝工作Z最迟完成时间－工作Z最早完成时间，故工作Z最迟完成时间＝工作Z最早完成时间＋工作Z的总时差＝12＋7＝19（天），则工作Z的最迟开始时间＝工作Z最迟完成时间－工作Z持续时间＝19－6＝13（天）。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]