[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-92822":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},92822,64,1,"单选题","某工程网络计划实施过程中，工作B的总时差刚好全部被占用，则（ ）不会受到影响。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","该工作的最早完成时间",false,{"key":16,"text":17,"correct":14},"B","其紧后工作的最早开始时间",{"key":19,"text":20,"correct":14},"C","其后续工作的最早完成时间",{"key":22,"text":23,"correct":24},"D","工程总工期",true,"工作的总时差是指在不影响总工期的前提下，本工作可以利用的最大机动时间。本题中，工作B的总时差刚好全部被占用，即在不影响总工期的前提下，工作B可以利用的最大机动时间为零，故工程总工期不会受到影响。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]